Construction updates
-
Asphalt Grind & Overlay – 7th Ave NW
The service swap on 7th Ave NW has been successfully completed. Work was done on 2/7/25. Thank you for your patience and understanding throughout the interruptions. Continue reading
-
Progress Update
The service swap on 7th Ave NW has been successfully completed. Work was done on 2/7/25. Thank you for your patience and understanding throughout the interruptions. Continue reading
-
7th Ave NW Service Swap Update
The service swap on 7th Ave NW has been successfully completed. Work was done on 2/7/25. Thank you for your patience and understanding throughout the interruptions. Continue reading
-
Delay of Water Shut-Off
We will be shutting down the water on the night of February 20th, 2025. The shutdown is necessary to allow for upgrades to the water system to be installed. The effected area will be from… Continue reading
-
Delay of Water Shut-Off
We will be shutting down the water on the night of February 20th, 2025. The shutdown is necessary to allow for upgrades to the water system to be installed. The effected area will be from… Continue reading
-
Notice of Water Shut-Down 2/20/25
We will be shutting down the water on the night of February 20th, 2025. The shutdown is necessary to allow for upgrades to the water system to be installed. The effected area will be from… Continue reading
-
Construction Update
On track to complete water main installation on 1/30 (requires us disconnecting existing domestic and irrigation services from the old water main to the new one. Targeting 2/4/25 and 2/5/25 for service interruptions. All disconnected… Continue reading
-
Construction Update
On-site underground install will continue. Grading for building pads will begin. Site maintenance for weather will continue. Continue reading
-
Construction Update
On-site underground install will continue. Grading for building pads will begin. Site maintenance for weather will continue. Continue reading
-
Construction Update
Sewer work in the right of way on 7th street is complete. On-site sewer work in progress. On-site storm vault work is estimated to start the week of 9/30/24. Storm in ROW (7th) estimated to… Continue reading















