- BLD 3- Foundation complete, groundworks complete and slab pour is today
- BLD 2- Foundation is complete groundworks complete underground
- BLD 5- Foundation form work in process
- Frontage improvements on 7th expected to begin within the next month
- Framing start for BLD 3 projected to start next week.
- Framing start for BLD 2 projected to begin in June