• BLD 3- Foundation complete, groundworks complete and slab pour is today
  • BLD 2- Foundation is complete groundworks complete underground
  • BLD 5- Foundation form work in process
  • Frontage improvements on 7th expected to begin within the next month
  • Framing start for BLD 3 projected to start next week.
  • Framing start for BLD 2 projected to begin in June